We are expecting to participate in the following design reviews for the FTT/NAS & FLC:

Phase 1a

to:

Design reviews for the FTT/NAS & FLC:

Deleted lines 4-6:

Phase 1b

Changed lines 7-9 from:
to:

We have agreed to dispense with the FDR.

March 15, 2012, at 01:40 PM by 131.111.48.85 -
Changed lines 6-7 from:
to:
Interim Testing Report
December 2011
Changed line 10 from:
to:
December 01, 2010, at 03:27 PM by jsy1001 - Page moved to MROIFastTipTilt.ReviewDocuments from MROIFastTipTilt.DesignReviewDocuments
December 01, 2010, at 03:25 PM by jsy1001 - Page moved to MROIFastTipTilt.DesignReviewDocuments from MROIFastTipTilt.DesignReviews
August 06, 2010, at 12:50 PM by jsy1001 -
Added lines 1-14:

We are expecting to participate in the following design reviews for the FTT/NAS & FLC:

Phase 1a

Conceptual Design Review (CoDR)
September 2010

Interim Preliminary Design Report?:

Phase 1b

Preliminary Design Review (PDR)

Phase 2

Final Design Review (FDR)?